071619_YKBP_A3.pdf
July 16, 2019 www.broadcasteronline.com
PUC Gives Crowned
Ridge Wind Farm
Permit To Construct
Broadcaster Press 3
South Dakota PUC Approves Construction
Permit For Triple H Wind Project
PIERRE, S.D. – The South Dakota
Public Utilities Commission apPIERRE, S.D. — The South Dakota Public Utilities
proved a construction permit for
Commission today approved a permit, with condithe Triple H Wind project, a wind
tions, giving the go ahead for the construction of the
energy facility capable of generCrowned Ridge Wind Farm in northeastern South
ating up to 250.54 megawatts of
Dakota. Commission members Gary Hanson, Chris
energy in Hyde Co. The action by
Nelson and Kristie Fiegen made their decision at the
the commission came on July 9 at
regular PUC meeting in Pierre on Tuesday, July 9.
its regular meeting in Pierre.
The Crowned Ridge Wind Farm will cover 53,186
A settlement agreement preacres in Grant and Codington counties. It will be capa- sented by Triple H and PUC staff
ble of producing as much as 300 megawatts of energy was previously accepted by the
from up to 130 wind turbines. The wind farm is owned commission in May. Issues not
by Crowned Ridge Wind LLC, a wholly-owned indirect addressed in the settlement – fundsubsidiary of NextEra Energy Resources LLC. Northern ing for decommissioning of the
States Power Co., doing business as Xcel Energy, will
project, risk associated with ice
purchase the energy produced by the wind farm.
throw and risk to whooping cranes
Crowned Ridge Wind filed its application with the
– were presented at an evidentiary
PUC on Jan. 30, 2019, launching a statutory six-month hearing in late June. The commisreview period that included a public input hearing in
sion’s action this week was to rule
Waverly in March and an evidentiary hearing in Pierre on those issues and determine if a
in June.
permit should be granted.
The 2019 legislature revised the law, extending the
Triple H must adhere to 41 conreview period to nine months for wind energy permit
ditions specified by the commisapplications filed with the commission after July 1,
sion during the construction and
2019.
operation of the project. Shadow
Intervenors participating in the Crowned Ridge
flicker, sound level, land restoraWind docket included Allen Robish and Amber Christion after construction, potential
tenson of Strandburg; Kristi Mogen of Twin Brooks;
impacts to whooping cranes and
and Patrick and Melissa Lynch of Watertown.
ice throw are among the details the
Among the 46 conditions the PUC placed on the per- conditions address. Additionally,
mit are those that address sound levels and shadow
the commission voted to require
flicker experienced by nearby residences, the detecthe establishment of an escrow
tion of ice on turbine blades, monitoring of grouse
account specifically designated for
leks within the wind farm area once construction is
the future decommissioning of the
complete, and funding for the removal of the facilities, project.
known as decommissioning.
At Triple H’s request, the com“I truly believe that through the conditions we
mission also considered changing
specified today, we came up with a good product,”
the requirements to provide notice
stated PUC Chairman Hanson. “We go through this pro- to landowners and the commission
cess following the evidence that has been presented
prior to construction and allow the
and making certain we follow the law. We have to base applicant to begin construction
our decision on evidence, not our feelings,” he said.
on Aug. 1, 2019. After discussion,
“It’s been a grind to get to where we are today,”
commissioners voted to maintain
noted PUC Vice Chairman Nelson. “Having considthe standard 14-day requirement
ered all the evidence presented during this process, I
believe the applicant has met the burden required in
state law to obtain a permit. The operational aspects
of this project have to meet the requirements that the
PUC and the counties have established,” Nelson said.
Your opinion is something
Commissioner Fiegen spoke about the commiswe always want to hear.
Questions?
sion’s final decision, stating, “Today we have adCall, write us or contact
Comments?
dressed a lot of concerns brought to our attention dur- us via e-mail and let us Story Ideas?
know how we are doing.
ing the evidentiary hearing and through post-hearing
briefs. What we have landed on is a combination that
works for the residents of the area, for the applicant
and for the state.”
201 W. Cherry •Vermillion, SD 57069
605-624-4429 • classifieds@plaintalk.net
Crowned Ridge Wind estimates the wind farm will
cost $400 million and expects it to be completed by
2020. This wind farm is separate from the Crowned
Ridge II wind farm for which an application is expected
to be filed with the PUC. The commission will have
nine months to process that application, pursuant to
the new law, which took effect July 1.
The Crowned Ridge Wind Farm docket can be
viewed on the PUC's website at www.puc.sd.gov,
Commission Actions, Electric Dockets, 2019 Electric
Dockets, EL19-003 – In the Matter of the Application
by Crowned Ridge Wind, LLC for a Permit of a Wind
Energy Facility in Grant and Codington Counties.
for landowners and 30-day requirement for the commission.
Of the company’s request, PUC
Chairman Gary Hanson stated,
“From my standpoint, I like to
honor precedents and I prefer
consistency. We know that there
are timelines that work for us and
I dislike experimenting with them.
I understand the need to complete
the project during one construction season, but we also need to
ensure we provide proper notice
to landowners and allow adequate
time for citizens and communities
to prepare.”
Triple H filed its application
with the PUC on Feb. 6, 2019. At the
time the application was filed, state
law required the commission to
make a decision within six months
of receiving a wind energy facility
application. A public input hearing
was held in Highmore in March.
No one sought intervention in this
docket.
PUC Vice Chairman Chris Nelson
reflected on the community participation at the input hearing. “The
public input meeting for this particular wind farm was unlike most
that we go to. It was clear that the
applicant had done the legwork
with folks in the area when they
came out to support the project.
That goes a long way toward telling
us that things have been taken care
of,” Nelson said.
Commissioner Kristie Fiegen
also recognized the company’s
efforts at the local level and in
working with the commission. “The
applicant and the Highmore community have really done a great job
to make this a win-win situation
We’re
all ears.
Thank You!
Thanks to all my family and friends for
making my 80th birthday party so special.
Thanks to everyone who came or
sent cards and good wishes.
~Kay Powell~
MOVING
W
“BUILDINGS”
Design – Quality – Price
More Bang for Your Buck!
This will ensure that all kids in
Vermillion, SD will have a
hot lunch every day.
10,800 copies distributed with 27,000
readers per issue and now in a
larger, reader-friendly format!
Call 624-4429 to get your ad in!
&
Sale
508 West Main St., Vermillion
Friday, July 19th • 1pm – 8pm
Saturday, July 20th • 8am – 7pm
• Children’s Furniture and Toys • New Chicken Coop
• Piano • Furniture & Much More!
Since 1974 – FREE QUOTES
Call: 1-605-949-1382
westernlumberandsteel@gmail.com
Miracle’s Miracle Wish
For Free School
Lunches 2019-2020
for everyone in that community. I
greatly appreciate staff and the applicant working together to ensure
that we allow for the project, but
also provide protection for our
citizens,” she stated.
The proposed project, located
approximately 3.2 miles southwest
of Highmore, will include up to
92 wind turbines spread over a
27,247.5-acre area. The project
footprint will also include access
roads, underground collector lines
and fiberoptic cable, a collection
substation, one permanent meteorological tower, a 345-kV interconnection switching station, a sonic
detection and ranging unit, and
an operations and maintenance
facility.
Triple H has entered into two
power purchase agreements. Upon
completion of the wind facility,
it will supply Walmart with 150
megawatts of energy and 48 megawatts will be sold to a confidential
institutional buyer. The remaining 52 megawatts will be sold on
a merchant basis. The company
estimates the project will cost approximately $300 million to build
and expects to complete construction in 2020.
The Triple H Wind Project
docket can be viewed on the
PUC’s website at www.puc.sd.gov,
Commission Actions, Commission
Dockets, Electric Dockets, 2019
Electric Dockets, EL19-007 – In the
Matter of the Application of Triple
H Wind Project, LLC for a Permit
of a Wind Energy Facility in Hyde
County, South Dakota.
WE’LL MAKE THE PIZZA
YOU MAKE THE
DIFFERENCE
UP TO 20% OF YOUR
PURCHASE WILL GO TOWARDS
YOUR GREAT CAUSE
Little Miss
Any additional
South Dakota
donations made before
2019-2020
or after this date on the DATE: 7/24/2019
TIME: ALL DAY!
GoFundMe page @
Miracle’s Miracle Wish LOCATION: VERMILLION, SD
PHONE: 605-624-5513
For Free Lunches will
PROMO CODE:1007
go towards the
ORDER ONLINE AT
free lunches.
OPEN HOUSE
Bridal Shower
HONORING
Jeanette Nygaard
Bride to Be of Loren Waddle
Sunday, July 21st at 3:00pm
Valiant Vineyards Winery
1500 W Main St
Vermillion, SD
Jeanette is registered at Target and Bed Bath & Beyond
Valid at any NPC International owned locations
PIZZAHUT.COM
Quality products, affordable prices!
Call today, start tomorrow!
Get your ad in the..
Classifieds
Today!
15%
CALL
624-4429
•••
FAX
624-2696
•••
EMAIL
classifieds@plaintalk.net
•••
ONLINE
BroadcasterOnline.com
•••
DROP BY
201 W. Cherry, Vermillion
Discount on
All Services
• Roofing • Siding
• Gutters • Decks
• Windows
Call Steve or Lexee
Your Certified Exterior Experts
605-595-7809
Vermillion, SD • ironcladconstructionsd.com